March 1999
Province approves cost sharing,
June
City Borrowing Bylaw,
July
Membrane supply awarded,
July
Design starts,
August
Site clearing begins, |
November
Building shell/outside work complete,
March 2000
Membrane equipment arrives,
June 22, 2000
Plant placed in operation,
July 14 , 2000
Official Opening. |