The following are details of upcoming work being completed on the roundabout project.
May 11 - 23, 2020
· Finish installation of 300mm Sanitary Main on 4th Street
· Installation of 200mm Sanitary Main on Victoria Road North
· Installation of 200mm Sanitary Main on Victoria Road Southwest
· Set up Sanitary Bypassing
· 300mm Sanitary Tie-ins