[ARCHIVED] Week 1, August 15-21, 2016 - Roundabout Construction Update

Overview
The majority of the work will be done on the north side of the proposed roundabout off the existing road with minimal impact on traffic.
The existing concrete island will be removed at Wright St and Victoria St early in the week to allow traffic to be shifted to the
south side of Victoria St.

Traffic Management
North Side Work Zone – Single Lane Traffic Both Directions.
Speeds reduced to 30 k/h as per construction zone.
Victoria Street is narrowed at corner to reduce traffic before the construction zone.
Traffic Control personnel will be used to setup the work zone and during the removal of the concrete curb island on Wright St.